Truck Update 1/23/19

  • Purchased large hole saw and engine pre-heater wire
  • Fabricated long pilot shaft for large hole saw
  • Hole saw cut heater exhaust opening in habitat floor
  • Machined aluminum sleeve to finish heater passthrough hole
  • Bonded aluminum sleeve into heater passthrough hole
  • Replaced air dryer cartridge
  • Spliced engine pre-heater wire
  • Bonded oak trim to lower edge of bed opening
  • Measured width of shower tray edge
  • Received water tank quick disconnect fittings
  • Laid out bed deck on plywood
  • Researched water tank barb bulkhead fitting options
  • Cut bed deck
  • Started detail design of shower drains
  • Finalized design of water tank pick up and vent
  • Machined AN-4 bulkhead fitting into tank barb fittings
  • Finalized layout of bed deck ventilation
  • Worked on under subframe box locking ideas
  • Ordered ceiling track for shower curtain
  • Ordered battery cutoff switches