- Ordered and received tile
- Ordered and received LED eyeball lights
- Ordered and received under counter LED lights
- Ordered kitchen cabinet and locks
- Ordered 2 1/2″ receiver pintal
- Purchased marine adhesive for floor hardpoint bonding
- Created assembly sequence list
- Started passthrough design work
- Started electrical wiring plan
- Inspected position of floor on subframe
- Measured and inspected all panels and corner extrusions
- Trimmed foam to fit in hardpoint channel
- Dry fit forward lower extrusion and front panel
- Marked position of passthrough on back of cab